Second FuzEvent installation in UK at the Veolia, Tyseley EfW plant in Birmingham

The management of the Veolia ES Birmingham Limited (Tyseley EfW plant) has selected the FuzEvent High Level control system for two Steinmüller combustion lines. Dublix Engineering shall carry out installation and commissioning of the FuzEvent system during autumn of 2009.
 
The Tyseley plant operates 3 combustion lines (one hospital waste processing line and two municipal waste combustion lines). The FuzEvent system shall be installed on the two municipal waste combustion lines with an annual capacity of around 350.000 ton waste, the aim for the optimization project is to improve the combustion stability and thereby to increase the overall capacity of the plant.
The optimization project was initiated based on a feasibillity study carried out by Dublix Engineering in order define the oportunity to increase the capacity on the plant.
The Veolia group already operates the FuzEvent system on three combustion lines at the STVL Limoges plant in the south of France, the new project thereby extend the already established positive cooperation between Dublix Engineering and the Veolia group.
 
This optimization project is the second FuzEvent installation in UK.